The details of projects under construction are tabulated below:
| Sr. | Project | Location | Capacity (MW) | Commissioning Date | Cost (Rs. Crore) | ||
| Original | Status/ Revised | Sanctioned | Revised | ||||
|
Indigenous Pressurised Heavy Water Reactors (IPHWR)
|
|||||||
| 1 | RAPP-7* | Rawatbhata, Rajasthan | 700 | Jun-2016 | Commenced commercial
operation on 15.04.2026 |
12,320 |
22,924 |
| RAPP-8 | 700 | Dec-2016 | In advanced stage of commissioning (expected to be operational in
2026) |
||||
| 2 | GHAVP-1 | Gorakhpur, Haryana | 700 | Sep-2020 | Completion of
construction and commissioning is expected to be completed in about 6 years from First Pour of Concrete. |
20,594 |
Under revision |
| GHAVP-2 | 700 | Mar-2021 | |||||
| 3 | KAIGA-5 | Kaiga,
Karnataka |
700 | June-2026 | June-2031 | 21,000 | Under revision |
| KAIGA-6 | 700 | June-2027 | June-2032 | ||||
| 4 | PFBR | Kalpakkam,
Tamil Nadu |
500 | Sep-2010 | Mar- 2027 | 3492 | Under
revision |
|
Light Water Reactors (LWR) with Foreign Cooperation
|
|||||||
| 5 | KKNPP-3 | Kudankulam, Tamil Nadu | 1000 | Mar-2023 | Jun-2027 | 39,849 | 68,893 |
| KKNPP-4 | 1000 | Nov-2023 | Jun-2028 | ||||
| 6 | KKNPP-5 | 1000 | Dec-2026 | Jun-2029 | 49,621 | 69,437 | |
| KKNPP-6 | 1000 | Sep-2027 | Mar-2030 | ||||
*Already commenced production in April 2026. However, cost available on Twin Unit basis (RAPP-7 & RAPP-8)
The year-wise details of the funds sanctioned, released and utilized for each project under construction during the last five years are attached as Annexure.
The major reasons for delay in construction/ commissioning of projects in the recent past have been due to extensive design changes following the Fukushima incident in Japan, delay in supply of critical equipment, Covid-19 pandemic & related issues, delay in supplies from Russian Federation (for KKNPP), delay in execution of works by contractors at site on account of financial crunch / cash flow problems post Covid, difficult site soil conditions (at GHAVP), shortage of skilled contractor manpower, and the impact due to ongoing Russia-Ukraine and USA/ Israel-Iran geopolitical conflict.
To address the challenges, various measures are being implemented to ensure timely completion of the projects. The measures include, periodic project reviews at multiple levels in NPCIL & DAE, constant monitoring of progress of project activities, timely identification of constraints & making necessary mid-course corrections, frequent meetings with vendors/ contractors to resolve various issues and re-sequencing of construction activities to the extent possible, higher delegation of powers to various executives of NPCIL and constitution of Board sub-committee for monitoring of projects. In addition to this, bulk ordering of long delivery equipment has been adopted and many equipment are under manufacturing/ progressive delivery for various reactors being implemented in fleet mode to ensure timely supply of long lead items for the projects.
Upon progressive commissioning of the projects currently under construction, a cumulative capacity of 8000 MW would be added to the national grid.
Annexure
The year-wise details of Equity Sanctioned, Released and Utilized for each project under construction during the last five years are tabulated below:
Amount in Rs. Crore
|
Name of the Project |
2021-22 |
2022-23 |
2023-24 |
2024-25 |
2025-26 |
||||||||||
| Equity Sanctio
ned |
Equity Released | Equity Utilized | Equity Sanctio
ned |
Equity Released | Equity Utilized | Equity Sanctio
ned |
Equity Released | Equity Utilized | Equity Sanctio
ned |
Equity Released | Equity Utilized | Equity Sanctio
ned |
Equity Released | Equity Utilized | |
| GHAVP-1&2 |
540 |
141 | 141 |
1952 |
577 | 577 |
1990 |
254 | 254 |
2831 |
563 | 563 |
3042 |
631 | 631 |
| KKNPP-5&6 | 363 | 363 | 1375 | 1375 | 1585 | 1585 | 1924 | 1924 | 1806 | 1806 | |||||
| CMAPP-1&2 | 7 | 7 | 0 | 0 | 12 | 12 | 41 | 41 | 73 | 73 | |||||
| MBRAPP-1to 4 | 15 | 15 | 0 | 0 | 23 | 23 | 42 | 42 | 49 | 49 | |||||
| KAIGA-5&6 | 8 | 8 | 0 | 0 | 102 | 102 | 246 | 246 | 365 | 365 | |||||
| GHAVP-3&4 | 6 | 6 | 0 | 0 | 14 | 14 | 15 | 15 | 118 | 118 | |||||
| Total | 540 | 540 | 540 | 1952 | 1952 | 1952 | 1990 | 1990 | 1990 | 2831 | 2831 | 2831 | 3042 | 3042 | 3042 |
The year-wise details of Equity Sanctioned, Released and Utilized for PFBR during the last five years are tabulated below:
|
Name of the |
2021-22 |
2022-23 |
2023-24 |
2024-25 |
2025-26 |
||||||||||
| Equity Sanctioned | Equity Released | Equity Utilized | Equity Sanctioned | Equity Released | Equity Utilized | Equity Sanctioned | Equity Released | Equity Utilized | Equity Sanctioned | Equity Released | Equity Utilized | Equity Sanctioned | Equity Released | Equity Utilized | |
| PFBR | 550 | 550 | 550 | 272 | 200 | 200 | 200 | 200 | 200 | 1184 | 600 | 500 | 374 | 150 | 150 |
This information was given by the Minister of State (Ind. Charge) Science & Technology; Earth Sciences and Minister of State PMO; Personnel, Public Grievances and Pensions; Department of Atomic Energy and Space Dr. Jitendra Singh in a written reply in Rajya Sabha today.